Recommendation
No objection to the first phase of the proposed building modernization project, which includes reconfiguration of the existing rooftop cooling towers, additional height to be added to the existing rooftop elevator overrun, rehabilitation of the infill structure in Courtyard Six, as shown in material received and dated 2 November 2007. Note that the work scheduled for Phase I does not include perimeter landscaping and security elements nor the relocated entrance to the National Aquarium. The included items in Phase I conform to the previously approved concept. (Previous: CFA 16/MAR/06-4)