Recommendation
No objection to the issuance of a permit for the construction of a new bioretention facility on the site of an existing building, including the removal, protection, and planting of numerous trees, as shown in materials received and dated 6 March 2020 and supplemental materials received and dated 13 March 2020, 19 March 2020, 25 March 2020, 2 April 2020, and 8 April 2020, PROVIDED that the stone cladding at the new retaining walls of the facility match other site walls on the campus. Note: Any subsequent modifications to the approved design, including those made during DCRA technical review, must be resubmitted to the Commission for approval.