CFA 17/MAR/22-a
No objection to the final design for a replacement guard booth at the Quadrangle Loading Dock that serves the Freer and Sackler Galleries, Ripley Center, National Museum of African Art, Arts and Industries Building, and the Smithsonian Castle, per materials received 7 March 2022. Final design is consistent with approved concept. Refer to DC Historic Preservation Office.
CFA 17/MAR/22-b
No objection to final design for repairs to roof, paving, and steam tunnel at Lion-Tiger Hill (Great Cats Exhibit), per materials received 8 March 2022. Refer to DC Historic Preservation Office.
CFA 17/MAR/22-c
No objection to concept design for replacement of windows and doors, and facade repairs, per materials received 3 March 2022. Refer to DC Historic Preservation Office.
CFA 17/MAR/22-d
Project approved by delegation. See letter dated 10 March 2022. Final design conforms with the previous recommendations of the Commission. Refer to DC Historic Preservation Office.