SL 24-157
Returned without action. Permit submission for the installation of 16 replacement windows at two existing buildings, as shown in materials received and dated 6 September 2024, has been withdrawn at the written request of the applicant on 19 December 2024. Refer to the L'Enfant Trust for historic easement.
SL 25-031
No objection to the issuance of a permit for the installation of three fabric awnings, including two awnings without signs and one awning with a sign, at an existing building for Good Company Doughnuts & Cafe, as shown in materials received and dated 3 January 2025 and supplemental materials received and dated 15 January 2025. Previously proposed redundant signs on every awning have been eliminated from the project scope. Refer to the General Services Administration. Refer to the National Park Service. Refer to the National Capital Planning Commission. Refer to DC Historic Preservation Office. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.
SL 25-032
Returned without action. Permit submission for the installation of a 1.25 SF stainless steel wall plaque for Cornerstone at the Maine Avenue, SW, entrance to an existing building, as shown in materials received and dated 3 January 2025, has been withdrawn at the written request of the applicant on 7 January 2025.
SL 25-033
No objection to the issuance of a permit for the installation of a rooftop solar panel system at an existing house, as shown in materials received and dated 3 January 2025, pending the receipt of supplemental materials. Refer to DC Historic Preservation Office. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.
SL 25-034
No objection to the issuance of a permit for exterior modifications at an existing house, including the installation of 32 replacement windows, five doors, gutters, siding, and a rooftop air-cooled condensing unit; the conversion of an existing window to an egress window with a window well; and repairs to existing concrete steps, as shown in materials received and dated 3 January 2025 and supplemental materials received and dated 14 January 2025, pending the receipt of supplemental materials. Refer to DC Historic Preservation Office. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.
SL 25-035
No objection to the issuance of a permit for the installation of a rooftop solar panel system at an existing house, as shown in materials received and dated 3 January 2025 and supplemental materials received and dated 13 January 2025. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.
SL 25-037
No objection to the issuance of a permit for the removal of an existing balcony partition at the top floor of an existing building to combine two adjacent residential units, as shown in materials received and dated 3 January 2025. Staff notes with regret that a permit was issued for the removal of the balcony partition prior to referral for CFA review. Refer to DC Historic Preservation Office. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.
SL 25-038
Returned without action. Property is not within the jurisdiction of the Shipstead-Luce Act and is not subject to review by the Commission of Fine Arts.
SL 25-039
No objection to the issuance of a permit for the installation of replacement windows at eight dwelling units, including seven units on the first floor and one unit on the basement, an egress door, a new areaway, steps, retaining wall, a new opening and gate on the existing stone wall, and mechanical equipment; and the relocation of an existing laundry room from the first floor to the basement in an existing apartment building, as shown in materials received and dated 3 January 2025, PROVIDED that measures be taken to protect existing trees and pending the receipt of supplemental materials. Recommend avoiding all tree roots with a diameter greater than two inches during construction. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.
SL 25-040
No objection to the issuance of a permit for the installation of three replacement skylights at the rear roof of an existing house, as shown in materials received and dated 3 January 2025 and supplemental materials received and dated 13 January 2025. Note: Any subsequent modifications to the approved design, including those made during DOB technical review, must be resubmitted to the Commission for approval.